 Post subject: time and work question
PostPosted: Sat Nov 17, 2007 10:33 am 
Offline

Joined: Mon Oct 08, 2007 6:36 am
Posts: 2
Please help.

If John can complete a project in 30 days and Joe in 60 days, how long will they take to complete the project if they worked on the project on alternate days? John starts working on the first day.

I got an answer of 20 days. However OA is 40.


Top
 Profile  
 
 Post subject: work time - alternate days
PostPosted: Thu Oct 02, 2008 8:27 am 
Offline
Site Admin

Joined: Tue May 22, 2007 1:28 pm
Posts: 19
Hi Alex

A delayed response to your query. Apologies.

Your answer of 20 days is correct if they worked together. However, this question states that they worked on it on alternate days. i.e. , John works alone on day 1. Joe works alone on day 2 and then John works alone on day 3 and so on.

As John could complete 1/30th of the work in a day and Joe could complete 1/60th of the work in a day,
at the end of day 2, they would have completed (1/30 + 1/60)th of the work.

i.e., ((2 + 1)/60)th of the work gets done in 2 days
3/60th or 1/20th of the work gets done in 2 DAYS and not in 1 DAY.
Hence, they will take 20 * 2 = 40 days to complete the task.

________________________

CrackSAT - SAT Classes @ Chennai, India
Next SAT Weekday classroom program @ Chennai, India starts July 1, 2011
+91 44 4500 8484


Top
 Profile  
 
 Post subject: Re: time and work question
PostPosted: Wed Mar 18, 2009 7:14 am 
Offline

Joined: Mon Oct 08, 2007 6:35 am
Posts: 4
Will the answer not be different depending on who started working first?

John and Joe complete do not work at the same rate.


Top
 Profile  
 
 Post subject: Re: time and work question
PostPosted: Fri Mar 20, 2009 12:30 pm 
Offline
Site Admin

Joined: Tue May 22, 2007 1:28 pm
Posts: 19
Good point.

No. It will not make a difference in this case. 1/30 + 1/60 = 1/20. If the answer had been 3/20 or some such number where the reciprocal of the value would not have been an integer, it would have mattered as to who started first.

In this case, no.

________________________

CrackSAT - SAT Classes @ Chennai, India
Next SAT Weekday classroom program @ Chennai, India starts July 1, 2011
+91 44 4500 8484


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 4 posts ] 

All times are UTC + 5:30 hours


Who is online

Users browsing this forum: No registered users and 0 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum

Search for:
Jump to:  
cron
Powered by phpBB © 2000, 2002, 2005, 2007 phpBB Group

phpBB SEO